How to become a prosumer

The process from decision to a bidirectional meter — 9 steps

Most people are intimidated by the paperwork with EPS and the municipality. We'll show you exactly what happens, in what order, who does what, and how long it takes. No surprises.

60-90
days for the process
average duration
9 / 10
steps done by MySolar
you just sign
€0
paperwork cost
included in turnkey
Step 1 / 911% complete
Step 01
Who acts
MySolar

Decision and free site visit

1-3 daysConsultation + roof assessment + offer

We come to your address, survey the roof and orientation, estimate consumption, propose the optimal capacity, and provide a final turnkey offer — no obligation.

What MySolar does
  • On-site visit and measurement
  • Consumption and orientation estimate
  • Final written offer
What you do
  • You sign the contract and advance payment (optional)
Step deliverable
Contract and technical assessment
YouMySolarEPSMunicipality

All steps handled by the MySolar team

You just sign a few documents. The entire process with EPS and the municipality — from request to bidirectional meter — we handle on your behalf.

Start the process

Frequently asked questions

Can I go through the process on my own?
Yes, but the administration is extensive and requires technical knowledge. The MySolar team does 9 out of 10 steps on your behalf — you just sign a few documents.
How long does the whole process really take?
On average 60-90 days; most of it is waiting on EPS (technical conditions + project approval + technical acceptance). With the MySolar team, you don't wait — we track every deadline.
What happens with surplus electricity?
Prosumer status lets you send surplus electricity to the grid and use it later (in the evening, in winter). This is the so-called "net metering" model. You don't receive money, but you offset consumption.
Is a building permit required?
For residential systems up to 10.8 kW, usually not. For larger systems and industrial installations, yes — we handle the procedure with the municipality.
What happens if EPS rejects the request?
Rarely happens with a properly prepared project. If it does, the MySolar team files an appeal or adjusts the project at no extra cost.
Are there hidden costs after the contract?
No. MySolar's turnkey price includes everything — from design, supply, and installation to paperwork with EPS and technical acceptance. What you see in the offer is what you pay.